Item
Project Title
Employer
Site Place
Project Status
Contract Duration
Notes
1
Waste Water Treatment (Design, Construction, Installation)
Mobin Petrochemical Co.
Bushehr-Asaluye
93%
On going
EPC
2
EM, PM (Equipments and units)
Khuzestan Petrochemical Co.
Khuzestan-Mahshahr
3 yrs
-
3
Pipe rack fabrication
Esfahan Petrochemical Co.
Esfahan
Finished
4.5 Mnt
PC
4
PM and EM Electrical, telecommunication, ventilation
Marun Petrochemical Co.
Khuzestan- Mahshahr
1 yr
Spare part
5
Methanol Plant Commissioning
Zagros petrochemical Co.
2.5 yrs
Consultation
6
Nitrogen membrane Plant
7
Operation Units Overhaul
15 days
8
Distillation Plant Overhaul
Lavan Oil refinery Co.
Lavan Island
30 days
9
Visbreaker Unit Overhaul
Arak Refinery Co.
Arak
10
L.A.B Esfahan
40 days
11
Catalyst Regeneration Unit Overhaul
12
Tar porner
Jay Oil Refining Co.
12 days
13
Administration and support services
Esfahan Oil Refining Co.
1 yrs
14
Inventory and production services
15
Support and building maintenance services
4 yrs
16
PA drawings Design
6 Mnt
17
CNG Fuel Station (Design, Procurement and Construction)
HESA Co.
Open
EP